dc.description.abstractIn order to guarantee its operation and supply to users, a transformer substation must comply with reliability and security requirements, it starts with security requirements aimed to guaranteeing the quality of supply at every moment of its operation. In Colombia, this requirement is evaluated by the Mining and Energy Planning Unit (UPME) and the regional and departmental action plans, which are adjusted with the growth and expansion plans. However, if the substations and configurations used are not renewed and updated, they could begin to lack these requirements at the end of their useful life in a portion of their operation, limiting both reliability and safety. This project aims to project improvements to the substation in the center of the city of Barranquilla, which is part of the 110 kV distribution system, coming from two lines of the neighboring substations Oasis and Silencio. Based on real data of the current electrical network, a simulation will be carried out in DigSilent software, under these conditions a series of changes were made and alternatives were presented, taking into account the different regulations and plans that UPME has proposed for this substation.spa
dc.description.abstractUna subestación de transformación para garantizar su operación y suministro a usuarios debe cumplir con los requerimientos de confiabilidad y seguridad, siendo la seguridad un aspecto característico encaminado a garantizar la calidad del suministro en cada momento de su operación. En Colombia, este requerimiento está evaluado por la Unidad de Planeación Minero energética y los planes de acción regionales y departamentales, los cuales se ajustan con los planes de crecimiento y expansión. No obstante, si las subestaciones y configuraciones utilizadas no son renovadas y actualizadas podrían empezar a carecer de estos requerimientos al final de su vida útil en una porción de su operación, limitando tanto la confiabilidad como la seguridad. Este proyecto toma como finalidad proyectar mejoras a la subestación centro de la ciudad de Barranquilla, la cual hace parte del anillo de 110 kV proveniente de dos líneas de las subestaciones vecinas Oasis y Silencio. Partiendo de unos datos reales de la red eléctrica actual se realizará una simulación en el software DigSilent, bajo estas condiciones se realizaron una serie de cambios y se presentaron alternativas, teniendo en cuenta las diferentes normativas y los planes que la UPME tiene propuestas para esta subestación.spa
dc.format.mimetypeapplication/pdfspa
dc.language.isospa
dc.publisherCorporación Universidad de la Costaspa
dc.rightsAttribution-NonCommercial-ShareAlike 4.0 Internationalspa
dc.rights.urihttp://creativecommons.org/licenses/by-nc-sa/4.0/spa
dc.subjectReliabilityspa
dc.subjectBusbars configurationsspa
dc.subjectConfiabilidadspa
dc.subjectSeguridad operativaspa
dc.subjectSistemas de potenciaspa
dc.subjectConfiguración de subestacionesspa
dc.subjectOperating securityspa
dc.subjectPower systemsspa
dc.titleEvaluación de los requerimientos de operación de subestación centro del departamento del Atlántico frente al plan de expansión propuesto por la unidad de planeación minero-energética.spa
dc.typeTrabajo de grado - Pregradospa
dc.rights.accessrightsinfo:eu-repo/semantics/openAccessspa
dc.identifier.instnameCorporación Universidad de la Costaspa
dc.identifier.reponameREDICUC - Repositorio CUCspa
dc.identifier.repourlhttps://repositorio.cuc.edu.co/spa
dc.publisher.programIngeniería Eléctricaspa
dc.relation.referencesAntonio Gómez Expósito, J. L. (20003). Sistemas eléctricos de potencia. Madrid: Prentice Hall.spa
dc.relation.referencesCámara de comercio de Bogotá . (Mayo de 2018). Proyectos para expandir la generación eléctricas del país . Obtenido de https://www.ccb.org.co/Clusters/Cluster-de-Energia Electrica/Noticias/2018/Mayo-2018/Proyectos-para-expandir-la-generacion-electrica-en el-paisspa
dc.relation.referencesCELSIA. (2020). sistema interconectado nacional. Obtenido de https://www.celsia.com/wp content/uploads/2021/02/Documento-de-trabajo-sobre-el-Sistema Interconectado Nacional.pdfspa
dc.relation.referencesCentro de Despacho de carga SIC. (2016). Criterios de Diseño para las Nuevas Subestaciones del sistema de transmisión troncal del SIC .spa
dc.relation.referencesCREG. (noviembre de 1994). Resolución 003 de 1994. Obtenido de https://gestornormativo.creg.gov.co/gestor/entorno/docs/resolucion_creg_0003_1994.htmspa
dc.relation.referencesCREG. (2000). Resolución 006.spa
dc.relation.referencesCREG. (2008). Resolución 097.spa
dc.relation.referencesCREG. (2014). Metodología para renumerar la distribución de energía eléctrica . MinMinas.spa
dc.relation.referencesDigSilent. (2015). Power system solutions . Obtenido de https://www.digsilent.de/en/company.htmlspa
dc.relation.referencesEPM. (2021). Diccionario de servicios públicos . Obtenido de https://www.epm.com.co/site/home/diccionario-de-servicios-publicosspa
dc.relation.referencesGrigsby, L. L. (2012). Electric Power Subastations Engineering . Taylor & Francis Group.spa
dc.relation.referencesJohansson, T. V. (Mayo de 2011). Overview of Analytical Power System Reliability Assessment Techniques. Norwegian University of Science and Technology Norway. Obtenido de https://www.researchgate.net/publication/281269920_Overview_of_Analytical_Power_System_Reliability_Assessment_Techniquesspa
dc.relation.referencesLanda, J. v. (2010). Redes Eléctricas I. Universidad Nacional Autónoma de México.spa
dc.relation.referencesMantilla-Flórez, B., Silva-Ortega, J., & Candelo-Becerra, J. (2018). Fault Effect Analysis Based on Elements Loadability to Evaluate Reliability in Power Systems. IEEE Latin America Transactions, vol. 16.spa
dc.relation.referencesMartin, J. R. (2000). Diseño de redes de tierra en subestaciones eléctricas. Obtenido de Ingeniería Investigación y Tecnología, ISSN 2594-0732, I.4, 157-171: https://www.revistaingenieria.unam.mx/numeros/2000/v01n4-02.pdspa
dc.relation.referencesQuezada, G. A., Paz, E. L., & Sánchez, D. V. (2015). Análisis comparativo entre subestaciones eléctricas encapsuladas en SF6 y subestaciones convencionales. Instituto politécnico nacional.spa
dc.relation.referencesRamírez, C. F. (2019). Subestación de alta y extra alta tensión . Mejía Villegas S.A.spa
dc.relation.referencesSilva Ortega, J. I., Daza Guzmán, J. D., Candelo Becerra , J., Rueda López , J. C., Umaña , I. S.,spa
dc.relation.referencesSalas Navarro , K., . . . Palacio , B. A. (2017). Modelo de 75 nodos para evaluar la operación en estado estable de una red de sub-transmisión de energía eléctrica. Espacios.spa
dc.relation.referencesUniversidad del Valle. (2015). Subestaciones I. En Objeto de una subestación en un sistema de potencia (pág. Capitulo I).spa
dc.relation.referencesUPME. (2015). Plan de Expansión de referencia generación- transmisión 2015-2025. MinMinas.spa
dc.relation.referencesUPME. (2015). Plan energético nacional de Colombia: ideario energético 2050. MinMinas.spa
dc.relation.referencesUPME. (Julio de 2016). Proyección de la demanda de energía eléctrica y potencia máxima en Colombia. MinMinas. Obtenido de Proyección de la demanda de energía eléctrica y potencia máxima en Colombia: https://www.ccb.org.co/Clusters/Cluster-de-Energia Electrica/Noticias/2016/Julio 2016/Proyeccion-de-la-demanda-de-energia-electrica-y potencia-maxima-en-Colombiaspa
dc.relation.referencesUPME. (2017). Proyección Regional de Demanda de Energía Eléctrica y Potencia Máxima en Colombia. MinMinasspa
dc.relation.referencesUPME. (2021). Plan de Expansión energético 2015-2029. MinMinas.spa
dc.relation.referencesVélez, A. U. (2008). Miembros de la comisión de expertos.spa
dc.relation.referencesXM . (2020). Informe oferta y generación Abril.spa
dc.relation.referencesXM expertos en Mercado. (2019). Demanda de energía Nacional. Obtenido de Reporte integral de sostenibilidad, operación y mercado: https://informeanual.xm.com.co/demo_3/pages/xm/20-demanda-de-energia-nacional.htmlspa
dc.relation.referencesXM expertos en mercados. (2020). Sistema de Transmisión Regional . Obtenido de https://www.xm.com.co/Paginas/Transmision/sistema-de-transmision-regional.aspxspa
dc.type.coarhttp://purl.org/coar/resource_type/c_7a1fspa
dc.type.contentTextspa
dc.type.driverinfo:eu-repo/semantics/bachelorThesisspa
dc.type.redcolhttp://purl.org/redcol/resource_type/TPspa
dc.type.versioninfo:eu-repo/semantics/acceptedVersionspa
dc.type.coarversionhttp://purl.org/coar/version/c_ab4af688f83e57aaspa
dc.rights.coarhttp://purl.org/coar/access_right/c_abf2spa


Ficheros en el ítem

Thumbnail
Thumbnail

Este ítem aparece en la(s) siguiente(s) colección(ones)

Mostrar el registro sencillo del ítem

Attribution-NonCommercial-ShareAlike 4.0 International
Excepto si se señala otra cosa, la licencia del ítem se describe como Attribution-NonCommercial-ShareAlike 4.0 International